One special consideration of this project was that the Public Utility Commission of Texas (PUCT) must approve all new transmission lines one mile or longer prior to construction. A CCN application was submitted for approval, which included responses to questions regarding line routing, environmental impact, landowner and community involvement, and the overall need.

Tasks included:

  • Completed applications in accordance with the latest PUCT rules
  • Developed routing map, aerial photo and schematic attachments
  • Conducted public meetings
  • Developed required construction estimates and project schedules
  • Prepared and sent notices to affected landowners, electric utilities within five miles, and county and municipal authorities
  • Prepared environmental assessments
  • Consulted with legal counsel regarding filing/follow-up requirements
  • Prepared all documents with necessary attachments
  • Submitted monthly transmission construction progress reports