Dugway Standby Generator Replacement, Dugway Proving Grounds
Guernsey provided complete electronic security system (ESS) and A-E services for the design and renovation of the existing standby generation plant at the Dugway Proving Ground. The existing standby generator plant was inoperable and had not been in use for a number of years.
The project was initiated with an extensive survey by the
multi-discipline team including security; mechanical, electrical, and
structural engineers as well an architect. Existing conditions and the
location of major components were documented through field notes and
digital photographs. The existing cinderblock generation plant was
constructed adjacent to an older wood structure containing legacy diesel
generators.
It was determined through consensus of the design team and
the Government representatives that this building should be demolished
to provide space for the exterior heat exchangers as well as to reduce
the fire protection requirements associated with the adjacent wood
structure. The generation capacity of the new generation plant
was sized to handle the ten-year projected electric load provided by the
site. Four engine generator sets were installed to meet the 10 MW
projected peak load. A new control room was installed with SCADA
controlled switchgear to start the generators remotely for loss of
voltage at Ditto Substation. The new generation is connected to Ditto
Substation. New transmission switches were installed between Ditto and
English Village Substations as well as communications for loss of
voltage. Other electrical aspects of the design included protective
relaying, new overhead and underground conductors to the English Village
substation. T
The facility was equipped with an electronic security system that was interfaced with the existing Honeywell/Vindicator system. Additionally, the ATFP requirements of the local ATFP officer were met throughout the design. The fire detection and protection system was designed to also accommodate future integration with a mass notification system. This project was designed in approximately one-half the time that was anticipated at the time of task order award in order to meet the requirements of the ARRA program.